The City of Lee’s Summit is seeking to improve Douglas Street from Chipman Road to 2nd Street. The street will be improved to current standards with improved roadside drainage, new sidewalks on the west side of the roadway, and a shared-use path on the east side of the roadway.
Further information on the project will be provided in the
coming months.
Begin design project – November, 2022
Concept Meeting (online and in-person) – April 19, 2023
Preliminary Design Meeting – Summer, 2023
Final Design Complete – May, 2024
Construction – starting late 2024 / early 2025
A Conceptual Design Meeting will be held on April 19, 2023 at City Hall in the Strother Room. This meeting, which will be held in an “open house” format allowing participants to come and go between 5:00 p.m. and 7:00 p.m., will provide an opportunity for the public to see additional information about the project and some options under consideration. Public input is encouraged and an online, self-directed meeting will open at the same time. The online meeting will remain open for approximately two weeks, closing on May 8.
Here is the link to the online public meeting.